Type: General Category: General Tags: Subject: Data taking plan

Data taking plan

13:00 ~: 0.8 GeV for validating the RARiS energy, maximum 0.2M events

(There will be intervention from Kobe group)

15:20 ~ 16:00: 4 GeV, Strip + W-plate → we need to detach the DUT to install W-plate behind (this means we need to double check the alignment)

17:00 ~ 19:00: Detach MCP-PMT, intall AstroPix, remove W-plate

19:00 ~: RFSoC runs

~09:00: Finish data taking